August 2008
• Ingolstadt City sells a part of the foundry land (ca. 2, 1 ha) located next to Ingolstadt University premises to the Free State of Bavaria.
December 2008
• Within the Quantitative Target Agreements with the Bavarian State Ministry of Sciences, Ingolstadt University commits itself to double the number of new students to 1000 in total.
• In return, the State Ministry aims at financing the extension building with an area of 9710 m² and estimated costs of ca. 45, 7 Mill. €. The purpose of the program is to react promptly to the increasing number of students.
March 2009
• Completion of the architectural competition
• Winning design by Architect’s Office Klein & Sänger
• Campus expansion into the neighboring area (ca. 2,1 ha)
• Completion of the first construction stage until 2012 (planned)
• Construction budget to be finalized by the end of 2009
June 2009
• Construction of lecture room containers on the university campus for the transition period until completion of the new construction.